District » Bond at Work » Existing Facilities

Existing Facilities

bond water tower project

 

Approximately $20 million of the 2015 Bond and $3 million of the 2017 Bond were dedicated to maintaining existing facilities. Bonds are funding projects at existing Comal ISD schools in the areas of compliance and items associated with federal and state compliance laws. Items include the repair and/or replacement of critical systems from structural, roofing, elevator, power, plumbing, heating, ventilation and air conditioning to life cycle/deficiency items such as antiquated building system repairs, upgrades and deferred maintenance activities that had been postponed due to funding priorities.  

 

Below you will find bond projects for CISD's existing Facilities grouped by school. All bond projects are from 2015, unless marked 2017.

 

 

Onsite Drainage Improvements

ASES, CHMS, CLHS, CMS, GFES, HLES, RBES, SBMS, SVMS, SVHS, STZES, TPES

Elastomeric Coatings on exterior walls    

 

 

ASES, CHMS,  GFES, HLES, MVMS, RCES, SBMS, SES

Roof work

 

 

ASES, CHS, CHMS, CMS, GFES, MVMS, SVMS

Replace gym floor with rubber flooring

 

 

ASES, CMS, HLES, SES, SBMS, SVMS

Chiller replacement 

 

 

CMS, GFES (2017), HLES, MVMS (2017), RCES, SVHS (2017)

Entry security vestibules

 

 

CHMS, CLHS, MECHS

New agricultural facilities

 

 

CMS, SVHS

Install new cooling tower

 

 

ISES, KRES

Replace existing exterior wall pack lighting

 

 

CLHS, HLES

New addition for wrestling area

 

 

CHS

Replace existing playground canopy

HVAC Upgrades (2017)

 

SES

Add ADA access ramp to garden

 

 

STZES

Add concrete sidewalk, stairs, handrails in parking lot

 

TPES

Install metal panels over existing plaster walls

 

 

MVMS

Replace exterior ductwork at kitchen

Replace canopies at bus loop & gym

Classroom Interior Upgrades

GFES

New classroom addition to welding shop

Renovation to ROTC area

 

 CLHS

Install rock wall at large oak tree

Replace VCT in A & B wing

Replace canopie at band hall exit door

 

CHMS

 

Repairs to concession stand

 

 

SBMS

Modify concrete at electrial room

 

 

MES

Pour sidewalk next to basketball court/install handrail

 

KRES

Install canopies at wodshop

Insulate duct work in girl's dressing room

 

 